Leite Hardware Electronic Co., Ltd. , http://www.sz-diecasting.com
Many cables in the 750 blast furnace area have been in operation for more than ten years, and the insulation level has been reduced year by year, posing a safety hazard to the reliability and stability of the power distribution system. In order to eliminate the hidden danger of power supply, the Ministry of Energy has carried out the transformation of the cable insulation project in the area, and updated the insulated cables of four systems such as the 750 blast furnace substation equipment. Through the transformation, the safety and stability of the power supply system of the 750 blast furnace area will be significantly enhanced.
Recently, the stainless steel branch 750 blast furnace area cable insulation project was successfully renovated.